Printer-friendly version

Sunshine Villiage Skatepark 
brought to you by” Spohn Ranch Skateparks”

The project is now complete! CLICK HERE to see photos.

 

CLICK HERE for up to date information.

 

July 19, 2019- The project is now underway, please CLICK HERE to see photos of the project start!

 

 

 


Fletcher Lake Project

The Township of Neptune is completing a project jointly with Bradley Beach for the replacement of the retaining wall at the west end of Fletcher Lake.  The Township of Neptune noticed wall failure and actively closed portions of the sidewalk as a precautionary measure.  During that time inspections and structural engineers evaluated the failure of the wall and subsequently the Township of Neptune jointly with the Borough of Bradley Beach funded the ongoing project with capital funds. 

The project was designed and publicly bid and is now under construction.  The scope is the replacement of the failing retaining wall, new curbing and sidewalk and milling and paving of the portion of Pennsylvania Avenue adjacent to the project.  In addition new fencing is proposed as part of this project.

The contractor is onsite and the construction has commenced.  There will be temporary road closure for the subject portion of Pennsylvania Avenue for the project duration and detours in place. 

The Township of Neptune and the Borough of Bradley Beach has worked with the following to bring this project to fruition, Neptune Township Sewer Department, the Department of Public Works, Department of Engineering, Leon S. Avakian Consulting Engineers, CME Engineers and Compass Construction.

      


 


 

 

 

Loffredo Fields

 

The Township of Neptune has received a Monmouth County Open Space Grant to replace the Loffredo Field Game Field.  This grant is also supplemented with Township funds.  The scope of the work entails removal of existing grass, irrigation, fencing and subgrade.  Regrading and construction of new field with new irrigation, drainage, topsoil and sod.  The new field will be graded uniformly to drain properly.  There are also new paint, goal posts and amenities. 

See start of project photos below. 


We now have sod and a new irrigation system!

 

 


Tremont Drive & Brighton Avenue Force Main


The Township of Neptune is completing several large Sanitary Sewer Capital projects throughout the Township.  These projects are necessary for both maintenance and upkeep of the sanitary sewer systems that are aging or in need of replacement.  Currently the Township of Neptune is working on two (2) Force Main Projects in Shark River Hills.  One is a Force Main Replacement on Brighton Avenue for the Hillside Road Pump Station.  This project runs from Hillside Road to Lakewood Road.  The other project is the Force Main Replacement for the Tremont Drive Pump Station from South Riverside Drive to Tremont.  The goal of the projects is to replace the force main from the pump stations to the downstream gravity main.  These pipe runs have incurred multiple repairs over the past several years and have outlived their useful life expectancy.  The Township has publicly bid both jobs and awarded to the qualified lowest bid contractors.

Tremont Drive

The Tremont Force Main job is being funded through Sewer Capital. The contractor Jo-Med started at the downstream manhole on South Riverside to the connection to the station on Tremont.  There are some unique features to this job with the force main connection in and the depth of the gravity line into the station.  The dewatering for the install of the new gravity connection has taken several days as it is quite deep.  Below are photos of the dewatering prior to setting the deep manhole and the trench box around the connection of the new force main shut off and quick connect should a bypass to the station ever be needed.

        

 


Brighton Avenue

The Brighton Avenue Force Main job is also funded through Sewer Capital.  This job is a little more straight forward and runs new Force Main from the pump station on Hillside Road to the gravity manhole on Lakewood Road.  The contractor has started at the downstream gravity manhole on Lakewood Road and is working their way to the pump station on Hillside.  The contractor was able to leave the existing force main in place and not have to install a bypass while installing the new force main closer to the center of the roadway.  Earle Asphalt has progressed from the gravity manhole about ¾ of the way down Brighton Avenue toward the Hillside Road Pump Station.  The job is progressing on schedule and will also require a new Force Main Tie in at the pump station.  This will provide the Neptune Township Sewer Department the ability to quick connect and bypass the station should the power go down or the station go offline.  Below are some photos of the daily road restoration and progress.

  


         

 


 

Alberta Lake Restoration Project 

The Township of Neptune just completed a project at Alberta Lake which was funded in part by FEMA and capital monies.  The project was for the desilting of the lake, removal of debris and vegetation along the banks, new valves, fencing improvements and landscaping.  A walking path was also constructed along the lake with new aerators placed in the lake. 

The Township has completed the project within the schedule and budget.  The Township of Neptune has completed another successful project with the cooperation of the residents, the TNHA, the Department of Public Works, Department of Engineering, Leon S. Avakian Consulting Engineers  and Precise Contracting. 

 
 
Email Newsletter icon, E-mail Newsletter icon, Email List icon, E-mail List icon Sign up for our Email Alerts  

 

Upcoming Events

 
Monday, April 29, 2024 - 6:00pm to 11:30pm EDT

 
Wednesday, May 1, 2024 - 7:30pm EDT

 
Thursday, May 2, 2024 - 6:00pm EDT

  Please Note: Summer Hours begin the week of May 6th. Municipal (M-Th. 8am to 4pm & F- 8am to 1pm) Public Works: (M-Th 7am to 3pm & F- 7am to 12pm)